Key takeaways
- Dominion Energy said in 2024 that connecting data centers above 100 MW could take one to three years longer than before, for total waits of up to seven years in Northern Virginia.
- LBNL's Queued Up 2025 reports only 13% of capacity that requested interconnection in 2000 to 2019 reached commercial operation by the end of 2024; 77% withdrew.
- New large-load tariffs require long minimum commitments, such as AEP Ohio's requirement to pay for at least 85% of subscribed demand for up to 12 years.
- The working capital safe harbor is tolled for government delays on a completed application, but no guidance treats a utility's study or construction queue as such a delay.
- Generation and substation assets count in a QOZB's 70% tangible property test only if the QOZB owns or leases them and they are used in the zone.
Why is power the biggest risk for an Opportunity Zone data center?
Because it usually takes longer than anything else and the OZ rules penalize idle capital. Cushman & Wakefield's H1 2026 Americas update says power availability now decides where data center growth can happen, with a record 37.7 GW under construction.14 A site with land, fiber and zoning but no firm power date is not yet a project.
Dominion Energy said in 2024 that connecting data centers above 100 MW could take one to three years longer than before, for total waits of up to seven years in Northern Virginia.2 For an Opportunity Zone (OZ) project, the Qualified Opportunity Zone Business (QOZB), the operating company that owns the project, can hold cash for only 31 months under a single written working capital plan, or 62 months with overlapping plans.12 See data center power timelines and the Opportunity Zone clock.
What is the difference between load interconnection and generator interconnection?
Load interconnection connects the data center to the grid as a customer; generator interconnection connects a power plant to the grid as a supplier. They run through different processes and timelines.
- Load service. The data center applies to its local utility for service. The utility studies the load, may need new transmission or substations, and signs an electric service agreement. Timelines depend on the utility and the local grid.
- Generator interconnection. A power plant, including on-site or co-located generation that will export or synchronize with the grid, joins the regional transmission organization's queue. LBNL's Queued Up report tracks these.1
Fig. 1Median years from interconnection request to commercial operation, generators
- Projects built 2000 to 2007under 2 years
- Projects built 2018 to 2024over 4 years
Queues are also unreliable. LBNL found that only 13% of capacity that requested interconnection from 2000 to 2019 had reached commercial operation by the end of 2024, 77% had withdrawn and 10% was still active.1
What do new large-load tariffs require from data centers?
Long minimum payments and collateral. Utilities and regulators have adopted tariffs that make large new loads pay for capacity they reserve, so other customers do not carry stranded costs.
| Utility | Applies to | Key terms | Status |
|---|---|---|---|
| AEP Ohio | New data centers above 25 MW | Pay for at least 85% of subscribed demand for up to 12 years, including a 4-year ramp; financial viability proof, exit fees and collateral | PUCO order, July 9, 20253 |
| Georgia Power | New customers above 100 MW | Contract terms of 5 to 15 years, minimum billing, recovery of upstream costs; contracts reviewed by the PSC | Georgia PSC rule, January 23, 20254 |
| Dominion Energy Virginia (GS-5) | Loads above 25 MW with a load factor of 75% or more | Minimum payment of 85% of contracted transmission and distribution demand and 60% of generation demand; obligations begin January 2027 | Approved by the SCC, November 20255 |
These terms affect the capital stack. Collateral, deposits and minimum bills are real costs before the first tenant pays rent. For OZ purposes, cash posted as collateral is not tangible property, so a QOZB should plan whether collateral is posted as cash, a letter of credit or parent-company credit support (analysis; confirm with counsel). See the capital stack for an Opportunity Zone data center.
What are FERC and DOE doing about data center interconnection?
They are writing new rules for large loads and co-location, and the results are still arriving. On December 18, 2025, FERC found PJM's tariff unjust and unreasonable for lacking clear rules for co-located load and directed new transmission services for co-located load, with compliance filings due February 16, 2026.6
On October 23, 2025, the Secretary of Energy used section 403 of the DOE Organization Act to send FERC a proposed rulemaking on interconnecting loads above 20 MW, including hybrid load-plus-generation facilities, opened as Docket RM26-4-000.7,8 FERC said in April 2026 that it would act by the end of June 2026.9 Secondary sources report FERC then issued show-cause orders to the regional grid operators rather than a single final rule; confirm current status on FERC's docket page before relying on any outcome.
Can on-site or co-located generation shorten the timeline?
Sometimes, but it brings its own permits, fuel supply and interconnection questions. Recent large campuses show the range:
- Homer City, Pennsylvania: a former coal plant site being converted to a 4.5 GW gas-fired campus on more than 3,200 acres, with first turbine deliveries expected in 2026.11
- Talen and Amazon (Susquehanna nuclear): after FERC rejected an amended agreement to expand co-located load from 300 MW to 480 MW, the parties moved to a front-of-meter power purchase agreement ramping to 1,920 MW by 2032.10
- Meta Hyperion, Louisiana: the state commission approved three Entergy gas plants of about 2.26 GW, plus a roughly $1.2 billion transmission line, to serve the campus.16
Fig. 2Grid service versus on-site generation for an OZ data center
Most common
Utility grid service
- Utility usually owns the substation and lines
- Utility-owned assets are outside the QOZB's tests
- Timeline set by the utility's studies and upgrades
- Large-load tariffs impose minimum bills and collateral
Behind or in front of the meter
On-site or co-located generation
- Can be owned by the QOZB if inside the zone
- Counts in the 70% test only if used in the zone
- Air permits, fuel supply and turbine lead times
- Wind and solar credits limited for later projects
Credits matter for renewable supply. Public Law 119-21 ends the §45Y and §48E credits for wind and solar facilities placed in service after 2027 unless construction began by July 4, 2026, and Notice 2025-42 tightened the beginning-of-construction rules.13 Projects counting on new contracted solar or wind should confirm the supplier's credit position.
How do the Opportunity Zone rules treat power infrastructure?
By ownership and location. A QOZB must have at least 70% of the tangible property it owns or leases be qualified zone business property, which must be acquired by purchase from an unrelated party, meet original use or substantial improvement, and be used in a zone during substantially all of the holding period.15
- QOZB-owned substation, switchgear, generators and UPS inside the tract: qualifying tangible property if bought new.
- Utility-owned substation or transmission line: the utility's property, outside the QOZB's tests.
- Generation outside the tract: owned property that is not used in the zone, which counts against the 70% test.
- Payments to a utility for upgrades the utility will own: analysis only; these may not be tangible property of the QOZB at all. Confirm treatment with tax counsel.
Does a utility delay extend the working capital safe harbor?
Not clearly. The regulations toll the safe harbor for delay caused by waiting for government action on a completed application, where no other action can be taken to advance the project, and add up to 24 months in a federally declared disaster area.12 Many utilities are investor-owned companies, and no guidance treats their study or construction queues as governmental permitting. See the working capital safe harbor.
What should an OZ data center investor check about power?
Ask for documents, not maps. A transmission line near the site says little about available capacity.
Fig. 3Power diligence for an Opportunity Zone data center
- PassExecuted electric service agreementSigned with the utility, with a capacity amount and delivery date
- PassLoad and facilities studies completeUpgrade scope and cost allocation known
- WatchTariff obligations pricedMinimum bills, collateral and exit fees in the budget
- WatchPhased energization scheduleEach phase matched to a working capital plan
- WatchOn-site generation permitsAir permits, fuel supply, turbine delivery slots
- FailRelying on queue position aloneMost queued capacity never reaches operation
For how power drives site choice, see data center site selection inside Opportunity Zones and rural data centers and Opportunity Zones. For the full schedule, see the Opportunity Zone data center development timeline.
Common questions
How long does it take to get grid power for a large data center?
It varies widely by utility. Dominion Energy has cited total waits of up to seven years for loads above 100 MW in Northern Virginia. Other utilities with spare capacity can be much faster.
Does a power delay extend the Opportunity Zone working capital safe harbor?
Not reliably. Tolling applies to delays waiting for government action on a completed application. No guidance says a utility's queue qualifies, so projects should secure power before deploying most of their equity.
Can a QOZB own its own power plant?
Yes. Generation the QOZB buys new and places in service inside the zone can be qualifying tangible property. Generation located outside the tract counts against the 70% test.
What is a large-load tariff?
A utility rate for very large new customers, usually with long minimum payment terms, collateral and exit fees. AEP Ohio, for example, requires new data centers above 25 MW to pay for at least 85% of subscribed demand for up to 12 years.
Is the LBNL interconnection data about data centers?
No. LBNL's Queued Up report measures generators seeking to connect to the grid. It is useful for on-site or co-located generation, not for the time to get service as a customer.
Sources
Every numbered note in this guide links to the source below.
- 1.Lawrence Berkeley National Laboratory, “Queued Up: 2025 Edition,” 2025. emp.lbl.gov
- 2.Bloomberg via BNN Bloomberg, “Data centers face seven-year wait for power hookups in Virginia,” 2024. bnnbloomberg.ca
- 3.POWER Magazine, “Regulator approves AEP Ohio's landmark data center tariff,” 2025. powermag.com
- 4.Georgia Public Service Commission, “Media advisory: data centers rule,” 2025. psc.ga.gov
- 5.American Action Forum, “Virginia's New Data Center Electricity Rate Class,” 2025. americanactionforum.org
- 6.Morgan Lewis, “FERC Directs Co-Location Reforms in PJM,” 2025. morganlewis.com
- 7.Beveridge & Diamond, “DOE Invokes Rare Authority to Direct FERC to Accelerate Grid Access for Large Loads and Data Centers,” 2025. bdlaw.com
- 8.Federal Energy Regulatory Commission, “Interconnection of Large Loads to the Interstate Transmission System, Docket RM26-4-000,” n.d. ferc.gov
- 9.Holland & Knight, “FERC to Act on Large-Load Interconnection Docket in June,” 2026. hklaw.com
- 10.Utility Dive, “Talen, Amazon Susquehanna nuclear data center deal,” 2025. utilitydive.com
- 11.Data Center Dynamics, “Homer City and Kiewit unveil plans for 4.5GW natural gas-powered AI data center in Pennsylvania,” 2025. datacenterdynamics.com
- 12.Wipfli, “Final opportunity zone regulations released,” 2020. wipfli.com
- 13.Jones Day, “IRS Issues New Guidelines for Wind and Solar Tax Credits,” 2025. jonesday.com
- 14.IREI, “Cushman & Wakefield: Power availability redraws data center map as Americas development hits record 37.7GW,” 2026. irei.com
- 15.Legal Information Institute, Cornell Law School, “26 CFR 1.1400Z2(d)-1, Qualified opportunity funds and qualified opportunity zone businesses,” n.d. law.cornell.edu
- 16.Data Center Dynamics, “Entergy obtains approval to construct three gas facilities to serve Meta's 2GW data center in Louisiana,” 2025. datacenterdynamics.com
This website is for general information only. It is not an offer to sell, or a solicitation of an offer to buy, any security. Any offering will be made only through confidential offering documents, to eligible investors, where permitted by law. Opportunity Zone tax benefits depend on each investor's circumstances and on rules that can change; consult your own tax and legal advisers.
Continue reading
Developing a data center in an OZ · 10 of 12
← Previous: Data center construction costs and Opportunity Zone budgeting·All 90 guides