Key takeaways
- Data Center Watch counted at least 75 data center projects worth about $130 billion blocked or delayed in Q1 2026, and opposition groups rose from 396 to 833 in one quarter.
- Brookings found counties that got their first large data center saw private employment rise 4% to 5% over five to six years, with construction employment up 11%.
- Virginia's JLARC found a typical data center employs about 50 full-time workers, about half of them contractors, so overstating permanent jobs damages credibility.
- Property tax and PILOT payments are the largest durable local benefit; Loudoun County reportedly draws about 38% of General Fund revenue from data centers.
- New QOF and QOZB reporting rules will collect tract-level data including employee counts, so community commitments will be easier to check.
Why does community engagement decide whether a data center gets built?
Engagement matters because local approval, not capital, is now the binding constraint for many projects. Data Center Watch reported that at least 75 projects worth about $130 billion were blocked or delayed in the first quarter of 2026, roughly matching all of 2025, and that local opposition groups grew from 396 to 833 across 49 states1. Statewide moratorium bills were introduced in 14 states in early 20261.
Local governments are acting. St. Charles, Missouri adopted a one-year moratorium on new or expanded data center applications in August 20252. Tucson's city council voted unanimously to end Project Blue the same month3. Pima County, Arizona passed a 120-day moratorium in September 20264. In Jay, Maine, a mill-to-data-center conversion collapsed after local opposition5.
Fig. 1Local opposition is growing fast
- Projects blocked or delayed in Q1 2026
- 75+
- Value of those projects
- ~$130B
- Opposition groups at end of Q1 2026, up from 396
- 833
- States with statewide moratorium proposals in early 2026
- 14
Opportunity Zone projects carry an extra burden. The program targets low-income census tracts, and federal lawmakers have questioned whether data centers belong in it. In September 2026, Sen. Josh Hawley introduced the No Tax Breaks for Data Centers Act, which would exclude data centers from Opportunity Zone benefits; it had been referred to the Senate Finance Committee and was not law6. Expect residents and reporters to ask what the zone gets in return.
What do residents worry about with data centers?
The recurring concerns are electricity bills, water, noise and land use, and the cost of tax breaks. Each one has a factual answer a developer should prepare before the first public meeting.
| Concern | What residents ask | What to bring |
|---|---|---|
| Power bills | Will my rates rise to pay for your substation? | The utility's large-load tariff terms and who pays for upgrades |
| Water | Will you draw down our aquifer? | Cooling design, annual water estimate, source and discharge plan |
| Noise and generators | Will we hear it at night? | Noise study at property lines, generator test schedule, air permits |
| Land and views | Is this farmland becoming an industrial zone? | Site plan, setbacks, landscaping buffers, height limits |
| Tax breaks | Are we subsidizing a giant company? | Expected property tax or PILOT revenue by year and by taxing body |
| Jobs | How many local jobs, really? | Construction headcount by phase and a realistic permanent staffing plan |
Power is often the first question. Utilities have started shifting cost risk onto large loads. AEP Ohio's approved tariff makes new data centers above 25 MW pay for at least 85% of subscribed demand for up to 12 years7. Showing that kind of protection answers the rate question directly. Water use depends on cooling design: U.S. data centers used about 17.4 billion gallons directly in 20238, and closed-loop designs cut on-site use sharply. See water and cooling for Opportunity Zone data centers.
What does the evidence say about data center jobs and taxes?
The best evidence shows real but modest job gains and large property tax gains, so lead with taxes and construction, not permanent headcount. Brookings researchers found that counties receiving their first large data center saw total private employment rise 4% to 5% over five to six years, with construction employment up 11%; they also found naive estimates overstate the effect about threefold9.
Virginia's legislative auditor (JLARC) found a typical data center employs about 50 full-time workers, about half of them contractors, and that most of the industry's economic footprint is tied to construction10. On the tax side, Loudoun County reportedly draws about 38% of its General Fund revenue from data centers and has cut its real property tax rate from $1.145 to $0.805 per $100 since 201611. State sales tax exemptions are a different story: Good Jobs First estimates each permanent data center job costs at least $1 million in state subsidies12.
Fig. 2Benefits and costs a community should weigh
Benefits
- Property tax or PILOT revenue for schools and services
- Hundreds of construction jobs during build-out
- Roughly 50 permanent jobs at a typical facility
- Utility and fiber upgrades that can serve other users
Costs and risks
- Large power demand and possible grid upgrade costs
- Water use, depending on cooling design
- Noise, generator emissions and industrial land use
- State sales tax exemptions with low job yield
For a fuller treatment, see the economic impact of data centers in Opportunity Zones.
How should a developer engage the community, step by step?
Engage before the land closes, disclose the hard numbers early, and convert promises into signed agreements. The sequence below fits most projects.
Fig. 3A community engagement sequence for a data center
- 01
Listen first
Meet officials, schools, utility, neighbors
- 02
Publish facts
Power, water, noise, jobs, taxes
- 03
Public sessions
Before the zoning application
- 04
Adjust design
Setbacks, cooling, generator testing
- 05
Sign commitments
PILOT, host or benefits agreement
- 06
Report results
Annual jobs and tax updates
- Name a single local contact who answers questions for the life of the project.
- Use plain units: gallons per day, decibels at the fence line, dollars to each taxing body.
- Separate construction jobs from permanent jobs in every document.
- Explain the Opportunity Zone role honestly: it lowers investors' taxes in exchange for long-term equity in the zone.
- Offer local hiring and training targets you can meet, with reporting.
What goes into a community benefit agreement or PILOT?
A good agreement fixes payments and commitments in writing, with remedies if the project underdelivers. Payments in lieu of taxes (PILOTs) are common. In Genesee County, New York, PILOT and host-community payments for a Stream Data Centers project were projected at about $285 million over 30 years, slightly more than unabated property tax would have been13. In Independence, Missouri, the city's analysis estimated $651.5 million in PILOT revenue from a Nebius project, including $463.4 million for the school district, with payments rising if investment falls short13.
| Term | What it does |
|---|---|
| PILOT schedule | Sets annual payments by year and allocates them to schools, county and city |
| Clawback or true-up | Raises payments if promised investment or jobs fall short |
| Water and noise limits | Caps annual water use or fence-line noise, with monitoring |
| Local hiring | Targets for local construction and operations hiring, with reports |
| Community fund | Fixed annual contribution to local programs |
| Decommissioning | Bond or plan for removal if the facility closes |
How do the Opportunity Zone reporting rules affect community commitments?
Funds and their operating businesses must now report more data, which makes community claims checkable. The law added IRC §6039K and §6039L, requiring annual information about Qualified Opportunity Funds and the businesses they own, backed by a penalty of $500 per day, capped at $10,000 per return or $50,000 for funds with more than $10 million in gross assets14. Proposed regulations published September 11, 2026 would require census-tract-level reporting and items such as employee counts; they are not final15.
Treasury must also report to Congress on the impacts and outcomes of designations every five years16. The Government Accountability Office found the effects of the incentive to date were mostly unknown16. Developers who publish their own jobs and tax data each year will be ahead of that scrutiny. See Opportunity Zone reporting requirements and penalties.
Is engagement different at rural sites?
Yes. Rural sites have fewer officials, fewer existing industrial users and closer neighbors per decision, so a single hearing can decide a project. The rules make rural zones attractive: a zone made up entirely of rural area halves the substantial improvement threshold to 50%, and a Qualified Rural Opportunity Fund gives investors a 30% basis step-up after five years17. WIRED reported that more than 100 planned rural data center projects could qualify for the enhanced rural benefits18. That attention means rural projects should expect questions about who benefits.
Practical points for rural engagement: brief the county commission, school board and electric cooperative separately; address farmland and road use; and explain fire and emergency response needs. Our guides to rural data centers and buying land cover site issues. Communities can read the companion guide for economic developers and communities.
Common questions
How many permanent jobs does a data center create?
Fewer than many residents expect. Virginia's JLARC found a typical facility employs about 50 full-time workers, about half of them contractors. Construction employment is much larger but temporary.
Do data centers raise local electricity rates?
They can if upgrade costs are spread across all customers. Many utilities now use large-load tariffs; AEP Ohio's requires new data centers above 25 MW to pay for at least 85% of subscribed demand for up to 12 years.
What is the biggest local benefit of a data center?
Usually property tax or PILOT revenue. Loudoun County reportedly draws about 38% of its General Fund revenue from data centers. The size depends on local abatements.
When should a developer start engaging the community?
At the option stage, before the zoning filing. Concerns raised after an application is filed tend to harden into organized opposition.
Are data centers allowed in Opportunity Zones?
Yes. Data centers are not on the excluded business list. A bill introduced in September 2026 would exclude them, but it had not been enacted.
Sources
Every numbered note in this guide links to the source below.
- 1.Data Center Watch, “Q1 2026 Data Center Watch Report,” 2026. datacenterwatch.org
- 2.KCUR, “St. Charles one-year data center moratorium (report),” 2025. kcur.org
- 3.AZFamily, “Tucson City Council votes to end Project Blue,” 2025. azfamily.com
- 4.KJZZ, “Pima County passes 120-day moratorium on future data center projects,” 2026. kjzz.org
- 5.Site Selection, “Maine Shutdown 2.0: Mill Redevelopment Project Stymied by Data Center Resistance,” n.d. siteselection.com
- 6.Bisnow, “Senators Are Pushing To Kick Data Centers Out Of Opportunity Zones,” 2026. bisnow.com
- 7.POWER Magazine, “Regulator approves AEP Ohio's landmark data center tariff,” 2025. powermag.com
- 8.Lawrence Berkeley National Laboratory, “2024 United States Data Center Energy Usage Report,” 2024. eta-publications.lbl.gov
- 9.Brookings Institution, “New evidence on data center employment effects,” 2026. brookings.edu
- 10.Joint Legislative Audit and Review Commission (Virginia), “Data Centers in Virginia, Report 598,” 2024. jlarc.virginia.gov
- 11.Fox News, “Homeowners in heart of America's AI boom getting unexpected payoff,” 2026. foxnews.com
- 12.Good Jobs First, “Most States Fail to Disclose which Data Center Companies Get Huge Tax Breaks,” 2025. goodjobsfirst.org
- 13.The Batavian, “Proposed incentive package for data center includes higher property taxes,” 2025. thebatavian.com
- 14.RSM US, “New penalties for taxpayers in the One Big Beautiful Bill Act,” 2025. rsmus.com
- 15.Federal Register (GovInfo), “Information Reporting Regarding Qualified Opportunity Zones and Updated Qualified Opportunity Fund Certification and Decertification Procedures, 91 FR 57968,” 2026. govinfo.gov
- 16.U.S. Government Accountability Office, “GAO-26-108132, Opportunity Zones,” 2026. gao.gov
- 17.Internal Revenue Service, “Enhanced tax incentives for Qualified Opportunity Zone investments in rural areas,” 2025. irs.gov
- 18.WIRED via Slashdot, “Rural Data Centers Are in for a Big Federal Tax Break,” 2026. tech.slashdot.org
OZ Data Centers
Building or investing in an Opportunity Zone data center?
We sponsor the deals, manage the funds and run the operating businesses. Tell us about your capital, your land or your project.
This website is for general information only. It is not an offer to sell, or a solicitation of an offer to buy, any security. Any offering will be made only through confidential offering documents, to eligible investors, where permitted by law. Opportunity Zone tax benefits depend on each investor's circumstances and on rules that can change; consult your own tax and legal advisers.