Water and cooling for Opportunity Zone data centers

U.S. data centers used about 17.4 billion gallons of water directly in 2023, a figure LBNL expects to double or quadruple by 2028, and rising rack densities (about 120 kW for an NVIDIA GB200 NVL72 rack) are pushing new builds toward liquid and closed-loop cooling. For an Opportunity Zone project, cooling design is both a site question (is there water, and will the community accept its use?) and a tax question: cooling plant the operating business buys new and owns can be qualifying tangible property, and, in practitioners' analysis, landlord-run cooling helps show an active trade or business.

Reviewed
Reading time
6 min
Figures
4
Sources
12 cited

Key takeaways

  • LBNL estimates direct on-site water use by U.S. data centers at about 17.4 billion gallons in 2023, plus about 211 billion gallons used indirectly through electricity generation.
  • Rack density ranges from about 12 kW for a general-purpose CPU rack to about 40 kW for an air-cooled H100 rack and about 120 kW for a liquid-cooled GB200 NVL72 rack.
  • Microsoft reports a fleet water usage effectiveness of 0.30 L/kWh in FY2024 and says all new designs since August 2024 use closed-loop, zero-evaporation cooling.
  • Uptime Institute reports global average PUE hovering above 1.5, essentially flat for about six years.
  • Cooling plant the QOZB buys new from an unrelated party and uses in the zone can count toward the 70% tangible property test; landlord operation of cooling can support the active trade or business position (analysis, not settled law).

How much water do data centers use?

About 17.4 billion gallons (66 billion liters) of direct, on-site use by U.S. data centers in 2023, according to Lawrence Berkeley National Laboratory's 2024 report, with on-site use projected to double or quadruple by 2028.1,2 Indirect use through the electricity data centers consume was far larger: about 211 billion gallons in 2023.2

Most direct use comes from evaporative cooling, where water is evaporated to reject heat. Facilities that use air-cooled chillers or closed-loop systems use much less water on site but more electricity, which shifts water use to power plants. LBNL's 2025 update projects data centers at about 649 TWh, or 11.8% of U.S. electricity, in 2030 in its reference case, so both water and power demand are rising.10

Fig. 1Data center water and efficiency at a glance

Direct on-site water use, U.S. data centers, 2023 (LBNL)2
17.4B gal
Indirect water use through electricity generation, 20232
211B gal
Microsoft fleet water usage effectiveness, FY20243
0.30 L/kWh
Global average PUE, Uptime Institute 2025 survey4
above 1.5
LBNL estimates for U.S. data centers in 2023, Microsoft's reported fleet metric and Uptime Institute's global survey.1,2,3,4

What cooling systems do modern data centers use?

Three broad approaches, chosen mainly by rack density and climate. Rack density is the power drawn by one rack of servers, and it determines how much heat must be removed from a small space.

Fig. 2Power per rack by workload type

  • General-purpose CPU rackup to about 12 kW
  • Air-cooled H100 rackabout 40 kW
  • NVIDIA GB200 NVL72 rackabout 120 kW

kW per rack

As reported by SemiAnalysis. At about 120 kW per rack, the GB200 NVL72 requires liquid cooling; general-purpose racks can still be air cooled.5

Fig. 3Cooling approaches and their trade-offs

Evaporative (cooling towers, adiabatic)

  • Low electricity use for heat rejection
  • Highest on-site water consumption
  • Needs reliable water supply and discharge permits
  • Most exposed to drought and local opposition

Closed-loop (non-evaporative)

  • Little or no evaporative water use
  • Higher electricity use in hot weather
  • Microsoft says all new designs since August 2024 use closed-loop, zero-evaporation cooling
  • Shifts water use to the power supply

Direct liquid cooling

  • Required for the densest AI racks
  • Coolant loops to the chip or rack
  • Usually paired with dry coolers or chillers
  • Higher plant cost per MW
A general comparison based on common industry practice; actual water and power use depend on design and climate. Microsoft's closed-loop designs avoid more than 125 million liters of water per facility per year, by its estimate.3

Efficiency has plateaued. Uptime Institute reports global average power usage effectiveness (PUE), total facility power divided by IT power, hovering above 1.5 and essentially flat for about six years.4 New liquid-cooled designs can do better, but older air-cooled fleets keep the average high.

How does water affect site selection in an Opportunity Zone?

Water is a gating factor alongside power. Many Opportunity Zone (OZ) tracts are rural, where water systems may be small and agricultural users compete for supply. Before committing equity, a sponsor should confirm in writing what the local water and wastewater utility can serve, or whether on-site wells and treatment are needed. That is practical analysis, not a rule.

Climate and design interact. A closed-loop design reduces water demand but raises peak electricity demand, which may require more grid capacity. In states where EPRI projects data centers could exceed 20% of state electricity use by 2030, including Arizona, Nevada and Oregon, both constraints apply.11 See data center site selection inside Opportunity Zones and rural data centers and Opportunity Zones.

Why does water use matter for community approval?

Because it is one of the most visible local impacts and opposition is growing. Data Center Watch reports that at least 75 projects worth about $130 billion were blocked or delayed in the first quarter of 2026, and that opposition groups grew from 396 to 833 between the end of 2025 and the end of Q1 2026.9 Pima County, Arizona adopted a 120-day moratorium on new data center projects in unincorporated areas in September 2026.8

Publishing water use estimates, choosing closed-loop cooling and funding local water infrastructure can all help. Opposition delays also carry an OZ cost: a stalled approval can push spending beyond the working capital safe harbor. See community engagement for Opportunity Zone data centers.

How do the Opportunity Zone rules treat cooling equipment?

As tangible property, counted by who owns it and where it is used. A Qualified Opportunity Zone Business (QOZB) must have at least 70% of the tangible property it owns or leases be qualified zone business property: acquired by purchase from an unrelated party, original use in the zone (or substantially improved) and used in a zone for substantially all of the holding period.6

  • Chillers, cooling towers, coolant distribution units and dry coolers the QOZB buys new and installs in the zone count as qualifying property.
  • Cooling equipment the tenant buys and owns, such as rack-level liquid cooling, is the tenant's property and outside the QOZB's tests.
  • Off-site water mains, wells or treatment plants owned by a municipal utility are the utility's property.
  • Short-lived mechanical equipment acquired after January 19, 2025 may qualify for 100% bonus depreciation; the building shell does not.12

Why landlord-run cooling helps the active business test

The regulations say merely entering into a triple-net lease is not the active conduct of a trade or business, and a final-regulation example treats a landlord as active where on-site employees meaningfully take part in management and operations.7 A landlord QOZB that owns and operates the cooling plant, staffs critical facilities and provides cooling as a service has more defensible facts than one that hands the building to a tenant. This is analysis, not settled law; see data center lease structures in Opportunity Zones.

What happens when cooling must be upgraded during the 10-year hold?

It is new spending that can strengthen the asset base. Rack densities have risen fast, from about 40 kW for air-cooled H100 racks to about 120 kW for GB200 NVL72 racks.5 A data center designed for air cooling may need liquid cooling within a 10-year hold to stay leasable.

New cooling equipment bought from an unrelated party and placed in service in the zone is itself qualifying property. Replaced equipment that is sold before year 10 does not get the 10-year exclusion, and the fund has 12 months to reinvest any proceeds for its 90% asset test. Plan retrofits in the business plan from the start. See servers, equipment and the Opportunity Zone rules.

Fig. 4Water and cooling diligence for an OZ data center

  • PassWritten water and sewer capacity from the utilityVolume, timing and connection costs confirmed
  • PassCooling design matched to target rack densityLiquid-ready if AI tenants are targeted
  • WatchWater use disclosed to the communityEstimates published before hearings
  • WatchDrought and supply risk assessedBackup supply or dry cooling option
  • WatchOwnership of cooling plant decidedAffects the 70% test and active business facts
  • FailLocal moratorium riskA pending moratorium can stall approvals for months
Practical checks before the main equity tranche. Watch items are common sources of delay that can push spending past the working capital safe harbor.8,9

Common questions

How much water does a data center use?

It depends on cooling design and climate. LBNL estimates U.S. data centers used about 17.4 billion gallons directly in 2023, mainly through evaporative cooling. Closed-loop and air-cooled designs use far less water on site but more electricity.

Do AI data centers need liquid cooling?

The densest racks do. An NVIDIA GB200 NVL72 rack draws about 120 kW and requires liquid cooling, compared with about 40 kW for an air-cooled H100 rack.

Does cooling equipment count toward the QOZB 70% test?

Yes, if the QOZB owns or leases it, bought it from an unrelated party, placed it in service new in the zone and uses it there. Tenant-owned equipment is outside the QOZB's tests.

Can cooling upgrades during the hold count as Opportunity Zone property?

Yes. New equipment bought from an unrelated party and placed in service in the zone qualifies. Gain on equipment sold before year 10 is not covered by the 10-year exclusion.

Is water use a reason data center projects get blocked?

It is one of several. Data Center Watch reports at least 75 projects worth about $130 billion were blocked or delayed in Q1 2026, and local moratoria such as Pima County's in September 2026 have paused new approvals.

Sources

Every numbered note in this guide links to the source below.

  1. 1.Lawrence Berkeley National Laboratory, “2024 United States Data Center Energy Usage Report,” 2024. eta-publications.lbl.gov
  2. 2.Honolulu Civil Beat, “Data Centers Consume Massive Amounts Of Water. Companies Rarely Say Exactly How Much,” 2025. civilbeat.org
  3. 3.Microsoft, “Sustainable by design: Next-generation datacenters consume zero water for cooling,” 2024. microsoft.com
  4. 4.Uptime Institute, “Uptime Institute Global Data Center Survey 2025,” 2025. intelligence.uptimeinstitute.com
  5. 5.SemiAnalysis, “GB200 Hardware Architecture and Component Supply Chain,” 2024. newsletter.semianalysis.com
  6. 6.Legal Information Institute, Cornell Law School, “26 CFR 1.1400Z2(d)-1, Qualified opportunity funds and qualified opportunity zone businesses,” n.d. law.cornell.edu
  7. 7.Novogradac, “Opportunity Zones Final Regulations: A Detailed Look,” 2020. novoco.com
  8. 8.KJZZ, “Pima County passes 120-day moratorium on future data center projects,” 2026. kjzz.org
  9. 9.Data Center Watch, “Q1 2026 Data Center Watch Report,” 2026. datacenterwatch.org
  10. 10.Lawrence Berkeley National Laboratory, “United States Data Center Energy Usage Report: 2025 Update,” 2026. eta-publications.lbl.gov
  11. 11.EPRI, “Powering Intelligence 2026: Updated Scenarios of U.S. Data Center Electricity Use and Power Strategies,” 2026. esca.epri.com
  12. 12.BDO, “One Big Beautiful Bill Act Expands 100% Depreciation Expensing Opportunities,” 2025. bdo.com

OZ Data Centers

Building or investing in an Opportunity Zone data center?

We sponsor the deals, manage the funds and run the operating businesses. Tell us about your capital, your land or your project.

Start a conversation

This website is for general information only. It is not an offer to sell, or a solicitation of an offer to buy, any security. Any offering will be made only through confidential offering documents, to eligible investors, where permitted by law. Opportunity Zone tax benefits depend on each investor's circumstances and on rules that can change; consult your own tax and legal advisers.