Key takeaways
- An investor has 180 days from the date of a gain to invest it in a Qualified Opportunity Fund.
- A QOZB may hold cash for up to 31 months under a written working capital plan, and up to 62 months with overlapping plans for multiple cash infusions.
- Dominion Energy has said connecting data centers above 100 MW in Northern Virginia could take up to seven years in total.
- LBNL reports the median time from interconnection request to commercial operation for generators built in 2018 to 2024 was over four years.
- For investments made on or after January 1, 2027, the deferred gain is taxed at the earlier of a sale or five years, and the 10-year exclusion requires holding the QOF interest at least 10 years.
How long does it take to develop an Opportunity Zone data center?
Usually three to seven years from site control to a building drawing full power, depending mostly on how quickly the utility can deliver capacity. Vertical construction is the shorter part. Epoch AI's tracking of recent gigawatt-scale campuses found 1 to 3.6 years from start of construction to 1 GW of power, and NTT Facilities puts the traditional design-and-construction period for a large data center at 3 to 4 years.3,4
Power is the long pole. Dominion Energy said in 2024 that connecting data centers above 100 MW could take one to three years longer than before, for total waits of up to seven years in Northern Virginia.2 For on-site or co-located generation, Lawrence Berkeley National Laboratory (LBNL) reports that the median time from interconnection request to commercial operation exceeded four years for generators built in 2018 to 2024, up from under two years for those built in 2000 to 2007.1 For more on the grid side, see power interconnection for Opportunity Zone data centers.
| Phase | What happens | Typical duration |
|---|---|---|
| Site control and diligence | Option or purchase, zoning, title, environmental, tract confirmation | 3 to 9 months |
| Power study and utility commitment | Load study, facilities study, electric service agreement, deposits | 6 to 24 months |
| Permits and approvals | Land use, building, air permits for generators, water | 6 to 18 months |
| Utility and substation work | Transmission upgrades, substation, feeders | 1 to 4+ years |
| Building construction | Shell, mechanical and electrical plant, commissioning | 18 to 30 months |
| Energization and ramp | Phased power delivery and tenant move-in | 6 to 24 months |
Which Opportunity Zone deadlines apply to a data center project?
Five clocks matter, and they start at different times. Some run for the investor, some for the operating business and some for individual buildings.
- 180-day investment period. An investor generally has 180 days from the date of a sale to invest the gain in a Qualified Opportunity Fund (QOF). For §1231 gains the period starts on the date of sale, and partners in a pass-through can elect other start dates, including the due date of the entity's return.8
- QOF 90% asset test. The fund must hold at least 90% of its assets in Opportunity Zone property, averaged over two semiannual testing dates.12
- Working capital safe harbor. A Qualified Opportunity Zone Business (QOZB), the operating company that owns the project, may treat cash as reasonable working capital for up to 31 months under a written designation and schedule, and up to 62 months with overlapping or sequential plans for multiple cash infusions.6
- Substantial improvement. A purchased existing building must be improved by more than its starting basis within any 30-month period, or by more than 50% of its basis in a wholly rural zone.7,13
- Investor holding periods. For investments made on or after January 1, 2027, the deferred gain is included in income at the earlier of a sale or five years after the investment, with a 10% basis step-up (30% in a rural fund). After 10 years, the investor can elect to step basis up to fair market value on sale.9
Fig. 1The Opportunity Zone clocks for one investment
Day 1
Capital gain realized
180-day investment period begins
Day 180
Last day to invest in a QOF
QOF then invests in the QOZB for cash
Month 30
Substantial improvement window
For a purchased building, measured from acquisition
Month 31
First working capital plan ends
Cash must be spent substantially as scheduled
Year 5
Deferred gain taxed
90% included in a standard fund, 70% in a rural fund
Month 62
Outer limit with overlapping plans
Requires multiple cash infusions and a consistent plan
Year 10
Tax-free exit available
Elect basis equal to fair market value on sale
Year 30
Basis fixed at fair market value
Appreciation after the 30th anniversary is taxable
How does the development schedule line up with the OZ clocks?
Poorly, unless capital is staged. If the QOF raises all its equity at month 0 and the utility delivers power at month 48, the cash sits idle well past the first 31-month plan. The figure below overlays an illustrative 46-month schedule on the safe harbor periods.
Fig. 2Illustrative development schedule against the OZ clocks
Illustrative- Site control and diligence
- Power study and utility commitment
- Permits and approvals
- Building construction
- Energization and commissioning
- Working capital plan 1 (31 months)First cash infusion
- Overlapping plans, outer limit (62 months)Needs later infusions
- Substantial improvement window (30 months)Only for a purchased building
Three points stand out. First, land, power studies and deposits are spent early, which suits the safe harbor. Second, the largest outlays (construction) fall in months 18 to 42, straddling the end of the first plan. Third, a ground-up building on raw land meets the original use test, so the 30-month substantial improvement clock applies only if the project buys and converts an existing building.7 See the working capital safe harbor and the substantial improvement test.
How should a data center project stage its OZ capital?
Raise and deploy equity in tranches that each fit a written plan. The regulations allow overlapping or sequential safe harbor plans up to 62 months from the first infusion, but each needs its own written designation, schedule and non-de minimis cash infusion, and the plans must form an integrated whole.6,5
Fig. 3A staged capital plan for an OZ data center
- 1
Seed tranche
Land, studies, deposits and design under plan 1
- 2
Power milestone
Signed electric service agreement and energization date
- 3
Construction tranche
New infusion and plan 2 sized to the build schedule
- 4
Construction loan
Debt funds vertical work after equity
- 5
Energize and lease
Placed in service; plan cash fully spent
Staging affects investors too. Each investor's 180-day period runs from its own gain, so a fund with several closings may take money over many months. Capital called later starts a later five-year and 10-year clock for that investor. See how a data center Opportunity Zone fund works.
What happens if the utility or permits are delayed?
Some delays toll the safe harbor and some do not. The regulations toll the period when the delay is attributable to waiting for a government action on a completed application, but only where no other action could be taken to advance the project during the delay. A QOZ in a federally declared disaster area can receive up to an additional 24 months.5
Whether a utility's study queue or its construction schedule counts as a governmental permitting delay has not been addressed in guidance. Many utilities are investor-owned companies, not government bodies, so a project should not assume tolling. Notice 2026-55 asks for comments on whether a QOZB should be allowed to modify an existing working capital plan, so this area may change.10
What happens between energization and year 10?
The project shifts from build to operate, and the QOZB must keep passing its tests every testing date. JLL reports tenants are signing leases for 2028 deliveries, which suggests that a project energizing on schedule can have its revenue in place by years four or five.11
- Year 5: investors owe tax on 90% of the deferred gain in a standard fund (70% in a rural fund), so many projects plan a refinancing or distribution around this date.9
- Years 5 to 10: IT and some mechanical equipment is replaced. Replacements must be bought from unrelated parties and placed in service in the zone to count as qualifying property.
- Year 10 and after: the investor can sell the QOF interest and elect basis equal to fair market value. See Opportunity Zone exit strategies after 10 years.
For the investor-level dates in one place, see Opportunity Zone key dates and timeline. The 30-year cap fixes basis at fair market value on the 30th anniversary, and Treasury has asked for comments on how that election works without a sale.10
Common questions
Can a data center be built within the 31-month working capital safe harbor?
The building often can, but the full project, including utility power, often cannot. Projects either stage capital into overlapping plans (up to 62 months) or wait to raise the main equity tranche until power is secured.
Does a utility interconnection delay extend the working capital safe harbor?
Not clearly. Tolling applies to delays waiting for government action on a completed application where nothing else can be done. No guidance says a utility's study or construction queue qualifies, so do not rely on it.
Does the 30-month substantial improvement rule apply to a new data center?
No, not for a ground-up building on raw land, which satisfies the original use test. It applies when a project buys an existing building, such as a warehouse or mill, and converts it.
When does the investor owe tax on the deferred gain?
For investments made on or after January 1, 2027, at the earlier of selling the QOF interest or five years after the investment. A 10% basis step-up applies at five years in a standard fund and 30% in a rural fund.
What is usually the longest phase of a data center project?
Securing and delivering utility power. Dominion has cited total waits of up to seven years for large loads in Northern Virginia, while NTT Facilities puts the traditional design-and-construction period for a large data center at 3 to 4 years.
Sources
Every numbered note in this guide links to the source below.
- 1.Lawrence Berkeley National Laboratory, “Queued Up: 2025 Edition,” 2025. emp.lbl.gov
- 2.Bloomberg via BNN Bloomberg, “Data centers face seven-year wait for power hookups in Virginia,” 2024. bnnbloomberg.ca
- 3.Epoch AI, “Data center buildout speeds,” 2026. epoch.ai
- 4.W.Media, “NTT targets 2028 to implement modular construction to halve hyperscale completion time,” n.d. w.media
- 5.Wipfli, “Final opportunity zone regulations released,” 2020. wipfli.com
- 6.ArentFox Schiff, “Qualified Opportunity Zones, the Final Regulations: What's New, What's Changed, and What's Stayed the Same,” 2020. afslaw.com
- 7.BDO, “Discussion of the Opportunity Zone Program Including Final Regulations,” n.d. bdo.com
- 8.Holland & Hart, “Taxpayer-Favorable Final Opportunity Zone Regulations Issued,” 2019. hollandhart.com
- 9.RSM US, “The OBBBA rekindles opportunity zones: What it means for real estate,” 2025. rsmus.com
- 10.Internal Revenue Service, “Notice 2026-55, Request for additional comments on issues under section 1400Z-2,” 2026. irs.gov
- 11.JLL, “North America Data Center Report Midyear 2026,” 2026. jll.com
- 12.KPMG, “Qualified Opportunity Funds: Mid-2022 Asset Testing Considerations,” 2022. tax.kpmg.us
- 13.Internal Revenue Service, “Notice 2025-50, rural areas and substantial improvement,” 2025. eitc.irs.gov
This website is for general information only. It is not an offer to sell, or a solicitation of an offer to buy, any security. Any offering will be made only through confidential offering documents, to eligible investors, where permitted by law. Opportunity Zone tax benefits depend on each investor's circumstances and on rules that can change; consult your own tax and legal advisers.