Key takeaways
- Cushman & Wakefield's 2026 guide puts all-in greenfield cost at about $8.9 million to $23.3 million per MW, up an average of 21% per MW since its prior edition.
- Power infrastructure is the largest component at 21% of greenfield cost, followed by core-and-shell and sitework (17%), contingencies (16%) and site acquisition (about 7%).
- JLL's average shell-and-core cost rose from $7.7 million per MW in 2020 to $10.7 million in 2025, with $11.3 million forecast for 2026.
- Land is excluded from the substantial improvement test, so a converted building must be improved by more than its own basis (50% in a wholly rural zone) within 30 months.
- Cash held by the QOZB must follow a written schedule consistent with the budget, for up to 31 months per plan and 62 months in total.
How much does it cost to build a data center per MW?
About $8.9 million to $23.3 million per MW all-in for a greenfield U.S. or Canadian project, excluding chips and GPUs, according to Cushman & Wakefield's 2026 Data Center Development Cost Guide. That range rose an average of 21% per MW since the previous edition, which covered Q4 2024.1,2
JLL tracks shell-and-core cost (the building and its core infrastructure, usually the landlord's scope). Its average global figure was $7.7 million per MW in 2020 and $10.7 million in 2025, a 7% compound annual rate, and JLL forecasts $11.3 million per MW in 2026.3,4 Tenant fit-out is a separate pool: JLL-derived coverage reports AI fit-out can cost up to about $25 million per MW, often more than the shell and core.5
Fig. 1Published data center cost benchmarks, $ millions per MW
- JLL shell-and-core, 2020 average$7.7M
- JLL shell-and-core, 2025 average$10.7M
- JLL shell-and-core, 2026 forecast$11.3M
- C&W all-in greenfield, low end (2026)$8.9M
- C&W all-in greenfield, high end (2026)$23.3M
$M per MW
Where does the money go in a data center budget?
Power infrastructure is the largest single component. Cushman & Wakefield's breakdown of greenfield cost shows power infrastructure at 21%, core-and-shell and sitework at 17%, contingencies at 16% and site acquisition at about 7%.1 The rest covers mechanical and cooling systems, other electrical work and soft costs.
Fig. 2Share of greenfield data center cost by component
- Power infrastructure21%
- Core-and-shell and sitework17%
- Contingencies16%
- Site acquisitionabout 7%
% of greenfield cost
A 16% contingency is a signal. Equipment lead times for transformers, switchgear and generators, and the 21% cost increase in one edition, mean budgets move. For an Opportunity Zone (OZ) project, a budget that moves also moves the working capital schedule, which must stay consistent with what is actually spent.
What does an illustrative OZ data center budget look like?
Below is an illustrative budget for a 40 MW building at $12 million per MW, within the Cushman & Wakefield range, applying its reported component shares. It is not a quote and real budgets vary widely by market, design and density.
| Component | Share | Amount | OZ treatment |
|---|---|---|---|
| Power infrastructure (substation, switchgear, generators, UPS) | 21% | $100.8M | Tangible property; short-life classes may qualify for bonus depreciation |
| Core-and-shell and sitework | 17% | $81.6M | Building is 39-year property; sitework often 15-year |
| Contingencies | 16% | $76.8M | Must still be scheduled in the working capital plan |
| Site acquisition | about 7% | $33.6M | Land: not depreciable, excluded from substantial improvement |
| All other (mechanical, cooling, other electrical, soft costs) | 39% | $187.2M | Mostly tangible property; soft costs capitalized into assets |
Two OZ consequences follow. First, almost everything except land is depreciable tangible property that the QOZB buys new, which suits the original use test. Second, the timing of each line becomes the schedule in the written working capital plan. For how the money is raised, see the capital stack for an Opportunity Zone data center.
How does the budget become a working capital safe harbor plan?
The budget is the plan. Under the regulations, a Qualified Opportunity Zone Business (QOZB) may treat cash as reasonable working capital for up to 31 months if it is designated in writing for acquiring, constructing or substantially improving tangible property in the zone, follows a written schedule consistent with ordinary start-up spending, and is spent substantially as planned.10 Overlapping or sequential plans can extend the period to 62 months from the first infusion.10
- Write the plan from the construction budget and schedule, line by line.
- Update the schedule as contracts are signed, with a record of why dates moved.
- Keep contingency inside the plan and draw it against identified scope.
- Do not park excess cash beyond what the schedule supports; the QOZB must keep nonqualified financial property under 5% of its property, and cash outside the safe harbor counts against that limit.13
See the working capital safe harbor for documentation details and the development timeline for how the plan lines up with power delivery.
How much must you spend to convert an existing building in an Opportunity Zone?
More than the building's own basis within 30 months, or more than half of it in a wholly rural zone. A purchased building that is not original use must be substantially improved: additions to its basis during any 30-month period after acquisition must exceed its adjusted basis at the start of that period.6 For property in a zone made up entirely of rural area, the threshold is 50%, effective since July 4, 2025.7
Land is excluded. Rev. Rul. 2018-29 holds that land under a building does not need to be separately improved and that only basis allocated to the building counts toward the hurdle.8 The regulations add an anti-abuse rule for unimproved land bought with no intent to improve it by more than an insubstantial amount.9
Fig. 3Substantial improvement hurdle for a converted warehouse
Illustrative- Purchase price20
- Less land allocation-5
- Rural zone: 50% threshold-7.5
- Rural hurdle: additions above $7.5M7.5
$ millions
Data center conversions usually clear this easily. A fit-out for power, cooling and structure on a mid-sized warehouse can cost many times the building basis. The purchase price allocation still matters and must be defensible. See converting industrial buildings into data centers and the substantial improvement test.
How should an OZ budget handle phasing and cost escalation?
Phase the build so each phase has its own budget, schedule and cash infusion. Large campuses are usually delivered in buildings or data halls as power arrives. Each phase can be matched to its own working capital plan, as long as the plans together stay within 62 months of the first infusion and each infusion is significant.10
Escalation should be priced in, not hoped away. Cushman & Wakefield's 21% average increase between two editions of its guide shows how fast costs can move.1 A budget with realistic escalation and a funded contingency is easier to defend as a schedule consistent with ordinary start-up spending than one that is rewritten every quarter. When the scope genuinely changes, document the reason at the time it happens.
Should the QOZB or the tenant pay for the IT fit-out?
Usually the tenant, but the choice has tax consequences on both sides. If the QOZB owns the servers and racks, they count in both the numerator and denominator of its 70% tangible property test, and short-lived equipment must be replaced with new qualifying property over a 10-year hold.13 If the tenant owns them, they are outside the QOZB's tests entirely.
Ownership also shapes depreciation. Public Law 119-21 made 100% bonus depreciation permanent for qualified property acquired after January 19, 2025, including MACRS property with a recovery period of 20 years or less; the building shell does not qualify.11 A cost segregation study separates the shell from shorter-lived electrical and mechanical components so the QOZB can claim bonus depreciation on the latter.12 See depreciation, bonus depreciation and Opportunity Zones and servers, equipment and the OZ rules.
Common questions
What is the average cost to build a data center per MW in 2026?
Cushman & Wakefield's 2026 guide puts all-in greenfield cost at about $8.9 million to $23.3 million per MW, excluding chips and GPUs. JLL forecasts average shell-and-core cost of $11.3 million per MW in 2026.
Does land count toward the Opportunity Zone substantial improvement test?
No. Only the building's basis sets the hurdle, and land does not need to be separately improved. Land must still be used in the business, and an anti-abuse rule applies to land bought with no intent to improve it.
Can the contingency budget be held under the working capital safe harbor?
Yes, if it is part of the written plan and schedule for building tangible property in the zone and is spent substantially as planned. Cash beyond what the plan supports counts as nonqualified financial property.
Do GPU and server costs belong in the QOZB budget?
Only if the QOZB will own them. In most leased data centers the tenant buys its own IT, which keeps that equipment outside the QOZB's tests. Cost benchmarks such as Cushman & Wakefield's exclude chips and GPUs.
Is the substantial improvement threshold lower in rural zones?
Yes. For property in a zone made up entirely of rural area, additions must exceed 50% of the building's adjusted basis within 30 months, instead of 100%. That rule has applied since July 4, 2025.
Sources
Every numbered note in this guide links to the source below.
- 1.IREI, “Cushman & Wakefield releases 2026 Data Center Development Cost Guide citing 21% rise in per-MW construction costs,” 2026. irei.com
- 2.CRE Daily, “Data Center Construction Costs Jump 21% Since 2024,” 2026. credaily.com
- 3.JLL, “2026 Global Data Center Outlook,” 2026. jll.com
- 4.Data Center Frontier, “JLL's 2026 Global Data Center Outlook: navigating the AI supercycle, power scarcity and structural market transformation,” 2026. datacenterfrontier.com
- 5.Data Center Dynamics, “Not a bubble: $3 trillion data center investment supercycle expected by 2030, JLL,” 2026. datacenterdynamics.com
- 6.BDO, “Discussion of the Opportunity Zone Program Including Final Regulations,” n.d. bdo.com
- 7.Internal Revenue Service, “Treasury, IRS provide guidance for Opportunity Zone investments in rural areas (Notice 2025-50),” 2025. irs.gov
- 8.Internal Revenue Service (hosted by Morris, Manning & Martin), “Revenue Ruling 2018-29,” 2018. mmmlaw.com
- 9.Stoel Rives, “Treasury Issues New Proposed Qualified Opportunity Zone Regulations,” 2019. stoel.com
- 10.ArentFox Schiff, “Qualified Opportunity Zones, the Final Regulations: What's New, What's Changed, and What's Stayed the Same,” 2020. afslaw.com
- 11.BDO, “One Big Beautiful Bill Act Expands 100% Depreciation Expensing Opportunities,” 2025. bdo.com
- 12.CBIZ, “Cost segregation bonus depreciation benefits under the OBBBA,” 2025. cbiz.com
- 13.Legal Information Institute, Cornell Law School, “26 CFR 1.1400Z2(d)-1, Qualified opportunity funds and qualified opportunity zone businesses,” n.d. law.cornell.edu
OZ Data Centers
Building or investing in an Opportunity Zone data center?
We sponsor the deals, manage the funds and run the operating businesses. Tell us about your capital, your land or your project.
This website is for general information only. It is not an offer to sell, or a solicitation of an offer to buy, any security. Any offering will be made only through confidential offering documents, to eligible investors, where permitted by law. Opportunity Zone tax benefits depend on each investor's circumstances and on rules that can change; consult your own tax and legal advisers.