Key takeaways
- A purchased building that is not original use must be substantially improved: additions to its basis during any 30-month period after acquisition must exceed its adjusted basis at the start of that period.
- For property in a zone made up entirely of rural area, the threshold is 50% instead of 100%, effective July 4, 2025 under the statute and Notice 2025-50.
- Land under the building does not have to be improved and is excluded from the calculation (Rev. Rul. 2018-29), so the purchase price allocation between land and building sets the size of the hurdle.
- A building that has been vacant for at least three years can be treated as original use, which removes the substantial improvement requirement for that building.
- Mills, factories and power plant sites can offer heavy floors, high ceilings and existing substations or transmission, but local opposition has ended at least one Maine mill conversion.
Why convert an industrial building into a data center?
Because the site may already have what new data centers struggle to get: heavy utility service, industrial zoning, water and a low purchase price. Many Opportunity Zones are former manufacturing districts, where land and building values are low and large structures sit vacant.
There are precedents. Sibley Mill in Augusta, Georgia, a former denim mill with 2.5 MW of on-site hydropower, was planned as a data center and technology park.11 Mayo Mill in Dover-Foxcroft, Maine, a woolen mill, was redeveloped with housing, commercial space and a data center with EPA brownfields support.12 At a much larger scale, the former Homer City coal plant in Pennsylvania is being converted into a planned 4.5 GW gas-fired data center campus on more than 3,200 acres.10 In Millinocket, Maine, Nautilus Data Technologies announced a 60 MW facility on part of the former Great Northern Paper mill site, described as in an Opportunity Zone; its current status is unconfirmed.14
Not every building works. Modern AI racks are heavy and dense: an NVIDIA GB200 NVL72 rack draws about 120 kW and requires liquid cooling.16 Floor loading, clear height, column spacing and room for generators and heat rejection can rule out a building no matter how good the tax math is. The broader framework is in Data centers in Opportunity Zones: the complete guide.
How does the substantial improvement test apply to a building conversion?
The building must be improved by more than its own adjusted basis within 30 months, or by more than 50% in a wholly rural zone. Opportunity Zone business property must be either original use in the zone or substantially improved by the Qualified Opportunity Zone Business (QOZB). Under §1400Z-2(d)(2)(D)(ii), property is substantially improved if, during any 30-month period beginning after acquisition, additions to its basis exceed its adjusted basis at the start of that period.1,2
Fig. 1Substantial improvement thresholds for an existing building
- Building in an urban or mixed zoneAt least 100%0%100%
Additions must exceed 100% of building basis
- Building in a zone made up entirely of rural areaAt least 50%0%100%
Additions must exceed 50% of building basis; effective July 4, 2025
Three refinements matter for conversions. First, land is excluded: it does not have to be separately improved, and only the basis allocated to the building sets the hurdle (Rev. Rul. 2018-29).4 Second, improvements do not have to be finished within the 30 months; the additions to basis must exceed the threshold in that period.3 Third, the final regulations allow aggregation, so qualifying new property on the parcel can count toward improving the property as a whole.6 How far aggregation reaches data center equipment should be confirmed with counsel.
An anti-abuse rule applies to land: unimproved land bought with the intent not to improve it by more than an insubstantial amount within 30 months cannot rely on the land exception.5 A conversion that leaves most of a large parcel idle should document the plan for the rest of the site.
The rural threshold comes from Public Law 119-21 and applies to determinations after July 4, 2025. Notice 2025-50 applies it to current zones that consist entirely of rural area, defined as anywhere other than a city or town of more than 50,000 people and the urbanized area next to it.7 Husch Blackwell flags adaptive reuse of rural buildings for data centers as one of the uses that benefit8, and Tax Notes has covered the rule in its analysis of data center tax planning.17 The rule is explained in The Opportunity Zone substantial improvement test.
Worked example: converting a mill into a 10 MW data center
Example (illustrative). A QOZB buys a vacant mill for $8 million. An appraisal allocates $3 million to land and $5 million to the building. The QOZB plans a 10 MW conversion with structural reinforcement, a new roof, electrical rooms and a utility service upgrade.
Fig. 2Required versus planned additions to building basis within 30 months
Illustrative- Required in an urban zone (more than 100%)$5.0M+
- Required in a wholly rural zone (more than 50%)$2.5M+
- Planned building improvements$30M
$ millions
The conversion clears either threshold by a wide margin. The real work is documentation: a defensible appraisal for the land and building split, a record of each addition to the building's basis by date, and a clear line between building improvements and separate equipment. Only the building's basis sets the hurdle, so a low allocation to the building makes the test easier, but that allocation must be supportable. Cushman & Wakefield's 2026 guide puts all-in greenfield cost at about $8.9 million to $23.3 million per MW excluding chips, a reminder that the conversion's total budget will dwarf the building's purchase price.15
The tax math for investors is the same as any Opportunity Zone deal; see Opportunity Zone tax savings: a worked example. A rural conversion owned through a rural fund can also give investors a 30% basis step-up at year five for investments after December 31, 2026.9
When is a converted building original use instead?
When it has been vacant long enough, or when the data center is a new building on the site. Under the final regulations, a building that has been vacant for at least three years before purchase can be treated as original use, so it does not need to be substantially improved.3 A new building constructed on an old industrial parcel is original use regardless of what stood there before.
| Path | When it applies | What the QOZB must show |
|---|---|---|
| Original use (vacancy) | Building vacant at least three years before purchase | Evidence of vacancy, such as utility records and leasing history |
| Original use (new construction) | New data center building on the parcel | First placed in service in the zone by the QOZB |
| Substantial improvement | Any other purchased building | Additions to building basis above 100% (50% rural) within 30 months |
| Leased building | Building leased on market terms from an unrelated party | Original use and substantial improvement do not apply to leased property |
New equipment installed in the building, such as switchgear, generators and cooling units bought from an unrelated party, is separately original-use property. For leased buildings, see Leased property rules for Opportunity Zone businesses.
What makes an industrial building suitable for data center use?
Power, structure and site room come first. The factors below are practical considerations, not tax rules.
| Factor | Why it matters | Opportunity Zone angle |
|---|---|---|
| Existing utility service and substation | Upgrading service is often the longest lead item | Delays can strain the 31-month working capital plan |
| Floor loading and slab | Liquid-cooled AI racks and battery rooms are heavy | Structural work adds to building basis |
| Clear height and column spacing | Affects airflow, containment and rack layout | Major rework adds to building basis |
| Yard and roof space | Generators, chillers and heat rejection need room | Yard equipment may be separate property |
| Water and wastewater | Cooling design and local permits | Closed-loop designs reduce dependence |
| Contamination and historic status | Cleanup and design limits | Brownfield and historic credits may stack |
Site-level screening, including fiber and flood risk, is in Data center site selection inside Opportunity Zones.
How do the 30-month and 31-month clocks work together on a conversion?
They run side by side, so the spending plan should satisfy both. The substantial improvement clock runs 30 months from a start date the QOZB chooses after acquisition. The working capital safe harbor lets the QOZB hold cash for up to 31 months under a written plan and schedule, with overlapping plans extending to a maximum of 62 months.18 A conversion that spends steadily on the building inside the first 30 months usually satisfies both.
Fig. 3Conversion sequence for an Opportunity Zone data center
- 01
Confirm power
Utility study and service upgrade path before closing
- 02
Acquire and allocate
Appraisal splits land and building basis
- 03
Adopt a written plan
Working capital schedule for the conversion
- 04
Improve the building
Track every addition to building basis by date
- 05
Install equipment
New, unrelated-party equipment is original use
- 06
Place in service
Begin operations and the active business tests
Power upgrades are the usual source of delay. See Data center power timelines and the Opportunity Zone clock.
What risks are specific to data center conversions?
Community response, hidden building conditions and power reliability. In Jay, Maine, a mill-to-data-center redevelopment collapsed after local opposition and the developer withdrew.13 Industrial sites can carry contamination, and older structures can hide problems that only show up during demolition. Federal policy is also in debate: September 2026 bills in Congress propose excluding data centers from Opportunity Zone benefits, but none had been enacted as of October 20, 2026. Engaging the community early is covered in Community engagement for Opportunity Zone data centers.
Common questions
Does the land have to be improved too?
No. Land is excluded from the substantial improvement test, and only the basis allocated to the building sets the hurdle. Land left idle with no intent to improve it can lose that treatment under an anti-abuse rule.4,5
Must the conversion be finished within 30 months?
No. Additions to the building's basis must exceed the threshold within a 30-month period, but the project does not have to be complete.3
Does the 50% rural threshold apply to new zones only?
No. It applies to property in any zone made up entirely of rural area for determinations after July 4, 2025, including current zones identified under Notice 2025-50.7
Do generators and cooling equipment count toward substantial improvement?
Improvements that add to the building's basis count directly. Separate equipment is generally its own original-use property, and the final regulations' aggregation rules may let some new property count toward the whole; confirm the treatment with counsel.6
What if the building has been vacant for years?
A building vacant for at least three years before purchase can be treated as original use, which removes the substantial improvement requirement.3
Is a former power plant site a good Opportunity Zone conversion?
It can be, because transmission and land are already there. Homer City in Pennsylvania is being converted into a planned 4.5 GW campus on more than 3,200 acres. Whether it qualifies depends on the site's tract status and the usual tests.10
Sources
Every numbered note in this guide links to the source below.
- 1.U.S. Government Publishing Office (GovInfo), “26 U.S.C. 1400Z-2, Special rules for capital gains invested in opportunity zones,” n.d. govinfo.gov
- 2.Electronic Code of Federal Regulations, “26 CFR 1.1400Z2(d)-1, Qualified opportunity funds and qualified opportunity zone businesses,” n.d. ecfr.gov
- 3.BDO, “Discussion of the Opportunity Zone Program Including Final Regulations,” n.d. bdo.com
- 4.Internal Revenue Service (hosted by Morris, Manning & Martin), “Revenue Ruling 2018-29,” 2018. mmmlaw.com
- 5.Stoel Rives, “Treasury Issues New Proposed Qualified Opportunity Zone Regulations,” 2019. stoel.com
- 6.Bisnow, “Final Opportunity Zone Regulations Released,” 2019. bisnow.com
- 7.Internal Revenue Service, “Notice 2025-50, rural areas and substantial improvement for qualified opportunity zones,” 2025. eitc.irs.gov
- 8.Husch Blackwell, “What the New 50% Substantial Improvement Rule Means for Real Estate Investors in Rural Opportunity Zones,” 2025. huschblackwell.com
- 9.Internal Revenue Service, “Enhanced tax incentives for Qualified Opportunity Zone investments in rural areas,” 2025. irs.gov
- 10.Data Center Dynamics, “Homer City and Kiewit unveil plans for 4.5GW natural gas-powered AI data center in Pennsylvania,” 2025. datacenterdynamics.com
- 11.GovTech, “Investors Eye Former Georgia Textile Mill as Home Base for Cybercenter,” n.d. govtech.com
- 12.U.S. Environmental Protection Agency, “Brownfields success story: Mayo Mill, Dover-Foxcroft, ME,” 2020. 19january2021snapshot.epa.gov
- 13.Site Selection, “Maine Shutdown 2.0: Mill Redevelopment Project Stymied by Data Center Resistance,” n.d. siteselection.com
- 14.Data Center Dynamics, “Nautilus to build $300m land-based data center in Maine,” 2021. datacenterdynamics.com
- 15.IREI, “Cushman & Wakefield releases 2026 Data Center Development Cost Guide citing 21% rise in per-MW construction costs,” 2026. irei.com
- 16.SemiAnalysis, “GB200 Hardware Architecture and Component Supply Chain,” 2024. newsletter.semianalysis.com
- 17.Tax Notes, “Tax Considerations for Data Center Projects,” 2026. taxnotes.com
- 18.ArentFox Schiff, “Qualified Opportunity Zones, the Final Regulations: What's New, What's Changed, and What's Stayed the Same,” 2020. afslaw.com
OZ Data Centers
Building or investing in an Opportunity Zone data center?
We sponsor the deals, manage the funds and run the operating businesses. Tell us about your capital, your land or your project.
This website is for general information only. It is not an offer to sell, or a solicitation of an offer to buy, any security. Any offering will be made only through confidential offering documents, to eligible investors, where permitted by law. Opportunity Zone tax benefits depend on each investor's circumstances and on rules that can change; consult your own tax and legal advisers.